"How long will this take?" It's the first question every homeowner asks. The answer: it depends. But not in a vague, unhelpful way. Kitchen remodel timelines are fairly predictable once you understand the phases involved.
Here's a realistic breakdown of what to expect, week by week, for a typical full kitchen remodel in the Greater Seattle area.
Pre-Construction: 2–6 Weeks
Before any demolition happens, there's planning work that needs to happen first. This is the phase most homeowners underestimate, and the one that makes or breaks the project.
- Design and material selection: 1–3 weeks. You'll finalize layouts, choose cabinets, countertops, tile, fixtures, and appliances. If you're decisive, this goes fast. If you like to take your time, budget more.
- Permits: 1–3 weeks depending on your city. Bellevue, Kirkland, and Redmond each have slightly different turnaround times. We submit permits as soon as the design is finalized.
- Material lead times: Custom cabinets can take 3–6 weeks to arrive. We order these as early as possible so they're ready when the demo is complete.
Week 1: Demolition
Demo is fast. Your old cabinets, countertops, backsplash, and flooring come out, usually in 2 to 3 days. It's loud, dusty, and dramatic. After demo, we assess the condition of the walls, floor, and any plumbing or electrical that was hidden behind the old kitchen.
This is when surprises can happen: water damage behind the dishwasher, outdated wiring that needs replacing, subfloor issues. A good contractor plans for this and communicates immediately if anything unexpected comes up.
Weeks 2–3: Rough-In Work
With the old kitchen stripped out, the trades come in. Electricians move outlets, add circuits for new appliances, and install recessed lighting. Plumbers relocate water lines and drains if the layout is changing. If there are any structural changes, like removing a wall or widening an opening, the framing work happens here.
This phase doesn't look exciting, but it's the most critical. Everything that goes inside the walls needs to be done right before we close them up. All rough-in work gets inspected before we proceed.
Weeks 3–4: Drywall, Paint, and Prep
Once inspections pass, the walls get patched, primed, and painted. The ceiling gets touched up. Any tile prep work (backing board, waterproofing) happens now. The room starts to look like a room again instead of a construction zone.
Weeks 4–6: Cabinets, Countertops, and Tile
This is where the finish work starts to take shape:
- Cabinet installation: 2–3 days for a standard kitchen. Everything is leveled, shimmed, and secured to the wall.
- Countertop template and install: The countertop fabricator comes to template after cabinets are in. Fabrication takes about a week, then installation is typically done in one day.
- Backsplash tile: Installed after countertops are in. Typically 1–2 days depending on the pattern and material.
Weeks 6–7: Fixtures, Appliances, and Finish Work
The final phase brings everything together:
- Sink and faucet installation
- Appliance delivery and hookup
- Pendant lighting and under-cabinet lighting
- Hardware on cabinets and drawers
- Touch-up painting and caulking
- Final cleaning
Week 7–8: Final Walkthrough and Handover
We do a detailed final walkthrough with you. We go through every cabinet, every drawer, every fixture. If anything isn't right, we fix it before we consider the project complete. You don't sign off until you're genuinely happy.
What Can Extend the Timeline?
Most kitchen remodels stay on schedule when they're planned properly. The most common causes of delays are:
- Custom cabinet lead times (especially during busy seasons)
- Permit delays in certain cities
- Unexpected structural or plumbing issues behind walls
- Client changes to the design mid-project
- Material backorders
We mitigate most of these through upfront planning and early material ordering. If a delay does happen, you'll hear about it the same day, not weeks later.
The Takeaway
A typical full kitchen remodel in the Greater Seattle area takes 6 to 10 weeks from demo to final walkthrough. With proper planning, material pre-ordering, and a clear schedule, most projects stay right on track. The key is choosing a contractor who plans thoroughly before they start, not one who figures it out as they go.